ATMS PHASE 3 OPERATIONS

Effective from Effective to Number Year Operator Issued
9/07/2020    1703  2020  GEN  9/07/2020 
 
APPLIES TO THE FOLLOWING ROUTE: - SPENCER JUNCTION TO WHYALLA

ATMS Safeworking - Risk control for Phase 3 operations
----------------------------------------------------------------------------------

As per Train Notice 1697-2020, on 16th July 2020 Advanced Train Management System (ATMS) will be commissioned as the Safeworking System between Spencer Junction and Whyalla.

During the initial period of operation (Phase 3), risk control number 3-A19 will be implemented and must be adhered to until practical completion has been achieved (Phase 4).

Risk control 3-A19 states - The Rail Traffic Crew of ATMS equipped trains must verify issued train authority details presented on the In Cab 'Driver Machine Interface' screen with the Network Controller via voice communication prior to entering ATMS territory.


Contact Details:
ATMS Operational Readiness Manager, G. Evans: 0408 438 267
ATMS Operations Officer, S. Curnow: 0429821942

AUHORISED BY: Mr Graham Harrison, Operations Interface, Interstate Network.