APPLIES TO THE FOLLOWING ROUTE: Mile End - Islington section
Optimisation of signalling system between Mile End and Islington Section (Stage 1 of 2)
On completion of commissioning work at 2359hrs on 13/07/2024 as advertised in TN 1806 / 2024, the following permanent infrastructure alterations apply.
New Absolute Signal 30 at 6.923km. 12V LED 3 Aspect signal. with 12V LED marker light New Absolute Signal 31 at 6.131km. 12V LED 3 Aspect signal. with 12V LED marker light
Both new LED signals will display aspects in accordance with the ARTC Addendum to the Code of Practice.
The following equipment has been decommissioned and removed.
Absolute searchlight Signal 31 at 6.626km Absolute searchlight Signal 30 at 6.916km Absolute searchlight Signal 66 at 6.640km
Authorised by: Operations Interface, SA/Vic, Interstate Network NCCW
|