TRACK SIGNAL INFRASTRUCTURE ALTERAT

Effective from Effective to Number Year Operator Issued
17/09/2024    2362  2024  GEN  17/09/2024 
 
Standing Notice 2362 dated 05/09/2024 is AMENDED (*) and REISSUED as below:

*This Standing Train Notice must be read in conjunction with Temporary Standing Notice 2466 dated 17/09/2024 and will remain in effect until it is cancelled.*

Wallan / Seymour Track and Signal Alterations

Effective From: 14/08/2024 2024

APPLIES TO THE FOLLOWING ROUTE: Somerton Loop to Benalla
-----------------------------------------------------------------------------------
On completion of work undertaken during the 60hr shut, (Monday 16/09/2024 - at 1800hrs or as advised) the following permanent track and signal alterations will apply.

Track and Signal Infrastructure Alterations
--------------------------------------------------------
- Wallan, Kilmore East, Tallarook, Goulburn River and Seymour to Mangalore.
- Wallan, 880 metre track slew of main line between signals WLN/4 and WLN/6.
*- Kilmore East, Signals KME/24, KME/28, EES661 and ES661 repositioned on to a new 9.5 metre cantilever gantry. Existing location 66.221km, new location 66.194km
- Kilmore East, Signals MPR/6 and MPR/18 repositioned on to a new 9.4 metre cantilever gantry. Existing location 69.790km, new location 69.766km.*
- Tallarook, Signals ES/862, EES/862, ES/863 and ESS/863 repositioned on to a new 9.3 metre cantilever gantry. Existing location 86.248km, new location 86.247km.
- Tallarook - Seymour Loop section, 1280 metre track slew of the main line between 95km and 98km in the vicinity of the Goulburn River.
- Seymour Loop, 2600 metre track slew of the west line between 99.500km and 103.000km.

Signal Indications and Permanent Track Speeds are unchanged as part of this work.

ARTC Project Engineer, Mr Tanishq Sarkar: 0436 117 695
Authorised by: Operations Interface SA/Vic, Interstate Network