Relocation of Signal 83/6
Commencing after the passage of 6PM9 at approx 0730hrs until 1700hrs on Monday the 5th September Downer EDi Works will require an Absolute Occupation of the section North Geelong "C" (SP 72/30, 72/32, 72/34 and 72/36) to Gheringhap Loop (SP 83/10, 83/12 and 83/14) for the purposes of relocating signal 83/6 from approximately 81.521 km to 81.458 km.
Signal 83/6 will be extinguished while the works are carried out.
The Safeworking Coordinator shall obtain the Absolute Occupation from the Train Control at Mile End who shall after assuring that the affected sections are clear of rail traffic apply blocking commands to all signals giving entrance to the occupied area.
Train Control (08) 8217 4232 Safeworking Coordinator Andy Armstrong (0437 096 654)
|