Wangaratta Track/Signal Aletrations

Effective from Effective to Number Year Operator Issued
27/02/2024    510  2024  GEN  27/02/2024 
 
APPLIES TO THE FOLLOWING ROUTE:
BENALLA TO CHILTERN

Track and Signal Infrastructure Alterations - Wangaratta:

The old East Track ‘Dive’ alignment incorporating Platform 2 Wangaratta will be removed from service, decommissioned, and subsequently removed.

Monday 11/03/2024 - at 1800hrs or as advised.
A new East Track alignment will be commissioned into service that will incorporate the existing Platform 1 at Wangaratta. East Track Banner Indicator WRT/6BI will be relocated and commissioned in a new location at 233.850km.

Wednesday 13/03/2024 - at 2359 hrs or as advised.
A new West Track alignment will be commissioned into service adjacent the new East Track. The new West Track alignment will not have an operational platform at the time of this change.

West Track Banner Indicator WRT/26BI will be relocated and commissioned in a new location at 233.850km.

All associated trackside signage will be relocated to the respective track in line with the above timing.

Signal Indications are unchanged as part of this work. Locations of Absolute Signals and points are unchanged as part of this work.

ARTC Project Engineer, Mr Tanishq Sarkar: 0436 117 695

Authorised by: Operations Interface SA/Vic, Interstate Network NCCW