APPLIES TO THE FOLLOWING ROUTE: -
ARTC MELBOURNE METRO LINE
ARTC VICTORIA SOUTH WEST LINE
Line Segment Newport to Laverton
Location Newport 10.990km to Laverton 16.160km
Worksite location 10.733km to 14.450km
Date and Time: 16:00 Monday 20 April 2026 to 18:00 Monday 31st August 2026
To allow construction of the new ARTC viaduct, the current ARTC standard gauge track will be temporarily moved onto a newly built track located where the old MTM West Track was situated. At the same time, the MTM West Track will be moved onto the newly built MTM viaducts during a planned SPA MTM Absolute Occupation.
A certificate of signalling will be issued prior to 16:00 Monday 20th April 2026 for the following changes to the standard gauge between Newport and Laverton, the below changes will remain in effect until 18:00 Monday 31st August 2026. - MTM East and West Lines elevated on viaduct above Maddox Rd - ARTC Track slewed from 11.855km to 12.938km on to decommissioned MTM West track - MTM West track gauge converted to ARTC Standard Gauge Track - Speed changed for up direction trains from 14.320km to 60km/h - resuming to line speed of 40km/h at 11.220km - Temporary speed restriction of 60km/h will be installed at 14.320km for up direction train movements - Predictor Board installed for Maddox Rd Level Crossing for up direction trains at 12.992km. - Whistle board installed for Maddox Rd Level Crossing for up direction trains at 12.703km. - Temporary speed restriction of 40km/h will be installed at 11.220km for down direction train movement until 14.320km, at which point trains can return to permanent line speed of 100km/h. - Permanent speed board of 80km/h will be covered up at 11.220km - Predictor Board installed for Maddox Rd Level Crossing for down direction trains at 11.807km. - Whistle board installed for Maddox Rd Level Crossing for down direction trains at 11.868km. - Champion Rd Fully Closed to the public with pedestrian fly over commissioned. - Conditions for Champion Rd Level Crossing in 10/30 Signal Removed. - 10/26P Signal Removed. - 10/26 Signal re-positioned on new track alignment (Wrong Sided Signal) at 12.503km. - New automatic pedestrian crossing commissioned at Maddox Rd Level Crossing. - New Booms and Flashing Light masts commissioned on west side of Maddox Rd Level Crossing.
During the August ARTC Commissioning Occupation from 01:00 Saturday 29th August until 18:00 Monday 31st August the Alignment will be shifted onto the newly constructed ARTC Viaduct.
ARTC NCCW Melbourne Metro Network Controller: 08 8152 8002 ARTC NCCW Victoria South West Network Controller: 08 8152 8001
Rail Lead: Chris Sotiropoulos 0427 415 988 Rail Safety Manager: Tom Deveson: 0468 552 510
Authorised by: Operations Interface SA/Vic, Interstate Network NCCW
|